Get the power flowing
Meter Installation and Energization Process
Getting a site ID is a common first step to setting up a new electrical connection or upgrading an existing service. Learn the steps involved with getting a new or temporary electrical service to your home or business.
Step 1: Have you confirmed ENMAX can give you the power you want?
Step 2: Get a Permit Number
Step 3: Get a Site Identification Number (Site ID)
Get a Site Identification Number (Site ID)
Please ensure you have reviewed steps 1 through 3 above before requesting a site ID.
Step 4: Select an electrical retailer
Step 5: Getting your site ready
Step 6: Request site energization
CT Site Readiness:
CT Request Form:
Installation will be scheduled during regular working hours (M-F; 8AM - 4 PM) unless otherwise requested. After-hours work can be requested and is subject to availability. Please note, an additional after-hours fee will apply. Request here.
Contact for CT Meter Site: 403-514-3780 or email RMC@enmax.com
Important resources
System capacity maps
Learn about the location and capacity available within the ENMAX Power distribution service territory.
Standards and regulations
Coming soon
Safety guidelines
Learn more about electrical and project safety.